Report to:                    Audit Committee

           

Date:                           20 September 2024

           

By:                               Chief Operating Officer

           

Title of report:              Internal Audit Progress Report – Quarter 1 (01/04/24 – 30/06/24)

           

Purpose of report:       To provide Members with an update on all internal audit and counter fraud activity completed during the quarter, including a summary of all key findings.  To also provide an update on the performance of the internal audit service during the period.

 

 

RECOMMENDATIONS: Committee Members are recommended tonote the report and consider any further action required in response to the issues raised.          

 

 

1.            Background

1.1       This progress report covers work completed between 1 April 2024 and 30 June 2024.

 

2.         Supporting Information

2.1       The current annual plan for internal audit is contained within the Internal Audit Strategy and Annual Plan 2024-25 which was approved by Audit Committee on 28 March 2024.

 

3.          Conclusion and Recommendations

3.1          Key audit findings from final reports issued during Quarter 1 are summarised in Annexe A.

 

3.2       Overall, of the 15 audits finalised during the quarter in which a formal audit opinion was given, 4 received an audit opinion of ‘substantial assurance’ (including one school), 9 received ‘reasonable assurance’ and 2 received an opinion of ‘partial assurance’ (one relating to the continued non-compliance with Council policy over the use of vehicles, resulting in an unchanged opinion of partial assurance, and the other, a school). There were no ‘minimal assurance’ opinions.

 

Graph to show assurance levels of formal audits completed in Quarter 1

 

 

*No opinion – typically, this tends to be proactive advice and support activity where, due to the advisory nature of the audit work, provision of formal assurance-based opinions is not appropriate.  It also includes grant certification work.

3.3       Although the same range of internal audit opinions is issued for all audit assignments (where an opinion is relevant), it is necessary to also consider the level of risk associated with each area under review when drawing an opinion on the Council’s overall control environment.  Taking into account these considerations, the Chief Internal Auditor continues to be able to provide assurance that the Council has in place an effective framework of governance, risk management and internal control. 

 

3.4       The overall conclusion above has, therefore, been drawn based on all audit work completed in the year to date and considers the management response to audit findings and the level of progress in subsequent implementation. As at the end of the quarter, 100% of high priority actions due had been implemented.

 

3.5       Progress against our performance targets (focussing on a range of areas relating to our service) can also be found in Annexe A (section 5).  All of these are rated as green and on track. 

 

 

 

ROS PARKER

Chief Operating Officer

 

Contact Officers:        Russell Banks, Orbis Chief Internal Auditor, Tel: 07824 362739,

Nigel Chilcott, Audit Manager, Tel: 07557 541803

           

 

BACKGROUND DOCUMENTS:     

Internal Audit Strategy and Annual Plan 2024/25